REM development transferring ahead in Better Montreal however issues stay – Montreal

Must read

Officers of the Réseau specific métropolitain (REM) are attempting to place a constructive spin on the progress of the all-electric gentle rail transit system for Better Montreal.

Greater than 3,000 staff are on 30-plus work websites attempting to ship the community to the general public by the tip of 2024.

To date, three of the 26 stations have been constructed and 13.7 km of 67 km of observe have been laid down.

Learn extra:
Quebec and Ottawa reach deal for REM station at Montreal airport

“We’re all the time alternatives to reinforce the person expertise and the expertise of those that will dwell subsequent to those techniques,” Harout Chitilian, vice-president of company affairs, growth and technique, stated at a press convention.

Officers expect the South Shore line linking Brossard with downtown Montreal to be completed and open to the general public by subsequent summer time.

Story continues under commercial

Exams on the rolling inventory have been achieved in all climate situations, with the automated and driverless trains reaching speeds of 100 km/h.

Chitilian expects the trains on this line will ultimately carry 60,000 riders a day and ultimately the complete community will entice 180,000 riders a day.

“That’s what’s anticipated within the authentic ridership research,” Jean-Marc Arbaud, the REM CEO stated on the press convention.

Learn extra:
Construction continues on future West Island REM stations without parking plan

However securing parking at two main stations within the West Island nonetheless hasn’t been achieved.

There isn’t any reserved parking for autos on the Fairview-Pointe-Claire and Kirkland stations regardless of each cease being constructed instantly adjoining to main purchasing malls.

“The service will probably be put in motion within the West Island in 2024, so we have now three years in entrance of us to deal with the options and tackle them to the general public,” Chitilian stated.

To date, no work has begun on the longer term Trudeau Airport station and that line is the final hyperlink scheduled to be completed on the complete community, with a supply date on the finish of 2024.

The revised price of the challenge is projected to be $6.9 billion, up from $5.5 billion in 2016.

Story continues under commercial


Click to play video: 'ARTM updates fare structure for Greater Montreal public transit'







ARTM updates fare construction for Better Montreal public transit


ARTM updates fare construction for Better Montreal public transit – Apr 29, 2021




© 2021 World Information, a division of Corus Leisure Inc.

- Advertisement -spot_img

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -spot_img

Latest article